CDC amendment · determined 25 July 2022
Bring the complying set back into line, while the DA is still running.
The development application was lodged and under assessment. Rather than wait to see how it landed, the complying certificate was amended in the middle of it — so the two approvals went on describing the same building instead of quietly drifting apart.
Two things changed: the reduced level of the alfresco slab, and the windows and doors. Both are exactly where the two pathways were going to collide. The alfresco slab level is set by how the building steps down the fall, and the DA was proposing to extend that alfresco. The windows and doors are the elements the house is judged by, and the DA was changing the roof above them.
This is the step most projects skip. It is why they arrive at a construction certificate holding a complying certificate that no longer matches what is being built — and then have to unpick it under time pressure, with a builder waiting.
CDC 2021/104/2 · modification to the RL of the alfresco slab and change of windows and doors